Naz City, Erbil, Kurdistan Region of Iraq (+964) 783 496 0952 info@razcompany.co Sat-Thu: 8:30am - 4:30pm

The project is in Basra governate south of Iraq, approximately 50 km to the west of Basra city and the area of the power station is 340 Acres. The Simple cycle gas turbine station which was constructed previously belongs to the Iraqi Ministry of Electricity (MOE). The existing simple cycle gas turbine power plant is composed of five (5) units of Siemens Model gas turbine SGT5 PAC 4000F &Gas Generator SGen5-1000A designed for 293 MW each and the total capacity of the Simple Cycle Power Plant is 1465MW, and this plant runs on Natural Gas.

KEY FACTS

  • The project is expanded by adding an environmentally friendly combined cycle with a capacity of 730MW. The Combined cycle belongs to Kar Electrical Power Production Trading FZE (KEPPT), contracts have been made with Siemens, Germany for supplying Steam Turbine and Generators and MHPS Dongfeng Boiler to supply Heat Recovery Steam Generator (HRSG) and the Balance of the Plant Equipment (BOP) has been provided from the various country according to approved specifications.
  • On 18th April 2018, the Construction of this project was awarded to RAZ with installation, civil, temporary works, water intake civil and erection, security, pipeline, and camp management. The project has reached total excavation works up to 500,000M³, sand gravel and backfilling around 260,000M³ with total pouring concrete and reinforcement up to 67,000M³, Road length around 7km. The steel structure of 8000 Ton, Equipment installation 430 set, piping 1800 DI, underground piping 22,500 M, Electrical cable 760 KM, cable tray 12200 set, panel 353 set, and manpower (local and international) 1600 person/day.
  • The combined cycle units have been successfully completed and it is generating power to supply to the Ministry of Electricity, Iraq according to the terms and conditions of the Power Purchase Agreement help to improve the efficiency and reliability of the Iraqi electrical grid system by producing additional electrical power without extra fuel consumption depending on exhaust gases of the simple cycle gas station.

The Power Plant Project is located in Basra Governate, South of Iraq, approximately 10 Km to the west from the Al-Basra city, and the area of the Power Station is 440 Acres. The Simple cycle gas station works on three types of fuel (natural gas, Gas oil, and heavy fuel), which was constructed previously, belongs to the Iraqi Ministry of Electricity (MOE). The station is composed of ten units (GE Model PG9171 and each unit is 125 MW) with a total capacity of the simple cycle of 1250 MW.

KEY FACTS

  • The project is expanded by adding an environmentally friendly combined cycle with a capacity of 650MW, it consists of five units. The Combined cycle belongs to Kar Electrical Power Production Trading FZ, contracts have been made with Siemens, Germany for supplying Steam Turbine and Generators and WUXI Boiler to supply Heat Recovery Steam Generator (HRSG) and the Balance of the Plant Equipment (BOP) has been provided from various countries according to approved specifications in a total of 91 shipments which weighted over 54,000 Tons (Approx.) and total volume of 165,000m3.
  • RAZ was awarded to conduct and complete pile works, civil works, site security works, site temporary facility construction and management works, water intake structure, pipeline detail design, and construction work. The project has reached a total of 6400 piles with a depth of 30-36 meters length, excavation works up to 360,000M³, sand gravel and backfilling around 230,000M³, with total pouring concrete up to 100,000M³, Road length around 10 Km, and at the peak manpower (local and international) reached up to 1350 person/day.
  • The combined cycle units help to improve the efficiency and reliability of the Iraqi electrical grid system by producing additional electrical power without extra fuel consumption depending on exhaust gases of the simple cycle gas station.